Version 2 - Current Planning Scheme
- Citation and commencement
- Part 1 About the planning scheme
- Part 2 State planning provisions
- Part 3 Strategic framework
- Part 4 Local Government Infrastructure Plan (LGIP)
- Part 5 Tables of assessment
- Part 6 Zones
- Part 7 Local plans
- Part 8 Overlays
- Part 9 Development codes
- Part 10 Other plans
- Schedule 1 Definitions
- Schedule 2 Mapping
- Schedule 3 Local Government Infrastructure Plan (LGIP) mapping and tables
- Schedule 4 Notations required under the Planning Act 2016
- Schedule 5 Land designated for community infrastructure
- Schedule 6 Planning scheme policies
- Appendices
9.3.6 Operational works
9.3.6.1 Application
This code applies to assessing all development within the Gladstone Regional Council area.
9.3.6.2 Purpose
- The purpose of the Operational Works code is to:
- Ensure all operational works (earthworks) are undertaken to appropriate levels and standard.
- Maintain a high standard of environmental amenity.
- Protect surface water and ground water.
- The purpose of the code will be achieved through the following overall outcomes:
- Operational works involving filling and excavation does not impact adversely on the site or the surrounding area in terms of the physical services and the environment or social values.
- The use of fill material that is safe and uncontaminated.
- Maintain the amenity of adjoining land, particularly the visual amenity of residential land.
- Operational works are located in areas that do not result in increased flooding and drainage problems on upstream and downstream property.
- Works are undertaken such that soil erosion is properly controlled to avoid unacceptable increased erosion and sediment loads into watercourses.
9.3.6.3 Assessment benchmarks
Table 9.3.6.3.1—Assessable development
Performance outcomes | Acceptable outcomes |
---|---|
Earthworks |
|
PO1 Earthworks are undertaken in a manner that:
|
AO1.1 Earthworks and retaining walls comply with the Engineering Design Planning Scheme Policy. |
AO1.2 Retaining walls are certified by a Registered Professional Engineer of Queensland. |
|
AO1.3 The extent of filling or excavation with a depth of 200mm or greater does not exceed 40% of the site. |
|
AO1.4 Excavating or filling is no greater than 1m, and height or depth and the combined height of retaining walls and fences does not exceed 2m. |
|
AO1.5 Soil to be used for filling if stockpiled for more than 1 month is stabilised and grassed. |
|
AO1.6 Retaining walls are set back from any boundary and are stepped or terraced so that landscaping can soften the visual impact. |
|
PO2 Earthworks maintain the efficiency of the road network and do not adversely impact upon residents or road infrastructure, including not creating any difficulty for access to the site. |
No acceptable outcome is nominated. |
PO3 Earthworks do not result in the contamination of land or water, and avoids risk to people and property. |
AO3 No contaminated material or acid sulfate soil is used as fill. |
PO4 Earthworks do not generate a dust nuisance. |
No acceptable outcome is nominated. |
Bridge and culvert work |
|
PO5 Bridges and culverts for flood immunity minimise traffic disruption, improve public safety, consider fauna habitat movement and allow for bikeways during and after construction. |
No acceptable outcome is nominated. |
Road design |
|
PO6 Roads providing access to the site are provided, constructed and maintained to a standard which is adequate for the traffic type and volume likely to be generated by the activities on site. |
AO6 External road works are provided in accordance with the requirements of the Engineering Design Planning Scheme Policy. |
Erosion and sediment control |
|
PO7 Earthworks do not create or worsen any flooding, drainage issues, ponding or an increase in flow directions or volumes, on the site or adjoining or nearby sites to ensure that:
|
AO7 Earthworks comply with flooding, drainage and erosion sediment control requirements of the Engineering Design Planning Scheme Policy. |
PO8 Construction activities for the development avoid or minimise adverse impacts on stormwater quality. |
AO8 The release of sediment–laden stormwater is avoided for the nominated design storm, and minimised when the nominated design storm is exceeded, by addressing design objectives listed below in Table 9.3.6.3.2 (construction phase) or local equivalent, for:
Note—An Erosion and Sediment Control Plan (ESCP) is prepared by a suitably qualified person that demonstrates:
|
PO9 Progressive rehabilitation of disturbed areas within the site is undertaken, as part of the completion of each stage of development, or where there are no stages, prior to the issuing of certificates of classification for building work or certificates of completion for operational work. |
No acceptable outcome is nominated. |
PO10 Development provides for a comprehensive rehabilitation program which ensures that disturbed areas are stabilised, temporarily and long term, within reasonable timeframes to minimise erosion on site and sediment discharge from the site. |
AO10 Development provides the following:
|
PO11 Premises in rural areas adopt a comprehensive approach to soil erosion and sedimentation management by:
|
No acceptable outcome is nominated. |
Weed control | |
PO12 Weed control practices and plant and equipment cleaning and inspection protocols are:
|
AO12 Reasonable steps have been taken to ensure that the vehicle or 'thing' being moved by road is free of reproductive material of any Class 1, 2 or 3 declared weeds. For example, compliance with the Queensland Guideline for Limiting Weed Seed Spread (DNR 2000). |
Amenity, acoustic and air quality |
|
PO13 Development is planned, designed and managed to ensure emissions and odours from activities achieve the appropriate air quality and noise objectives (measured at the receptor). Note—These levels are in accordance with the Environmental Protection (Air) Policy 2008, and Environmental Protection (Noise) Policy 2008. |
AO13 No acceptable outcome is nominated. |
PO14 Development does not generate vibration from activities that will affect the amenity of surrounding land uses. |
AO14 The development does not result in vibration impacts outside of the development site. |
Lighting |
|
PO15 External lighting is provided in urban areas to ensure a safe environment. |
AO15 Technical parameters, design, installation, operation and maintenance of outdoor lighting comply with the requirements of AS4282 – Control of the Obtrusive Effects of Outdoor Lighting. |
PO16 Outdoor lighting does not cause undue disturbance to any person, activity or fauna because of emission, either directly or by reflection. |
AO16 The vertical illumination resulting from direct, reflected or other incidental light coming from a site does not exceed 8 lux when measured at any point 1.5m outside of the boundary of the property at any level from ground level up. |
Operational works and electricity infrastructure |
|
PO17 The excavation, filling or laying of pipes within the vicinity of electricity supply infrastructure will not create potential damage or hazard. Note—Development involving filling, or excavation or laying of metal pipes on land contiguous to electricity supply infrastructure should be referred to the relevant electricity entity for safety advice on the proposed development. |
AO17.1 Excavation of filling does not occur within:
|
AO17.2 The laying of metal pipes does not occur within:
|
Table 9.3.6.3.2—Construction phase: Stormwater management design objectives
Issue | Design objectives | |
---|---|---|
Drainage control | Temporary drainage works |
|
Erosion control | Erosion control measures |
|
Sediment control |
Sediment control measures Design storm for sediment control basins Sediment basin dewatering |
|
Water quality | Litter and other waste, hydrocarbons and other contaminants |
|
Waterway stability and flood flow management | Changes to the natural waterway hydraulics and hydrology | For peak flow for the 1–year and 100–year ARI event, use constructed sediment basins to attenuate the discharge rate of stormwater from the site. |